LISP Flow Mapping Oxygen M2 Status
[docs.git] / docs / release-process / milestone-readouts / m2 / lispflowmapping.rst
1 =================
2 LISP Flow Mapping
3 =================
4
5 Please provide updates on any previously-incomplete items from prior milestone
6 readouts.
7 None
8
9 Functionality Freeze:
10 ---------------------
11
12 1. Final list of externally consumable APIs defined: Yes
13
14    - If you had Tentative APIs, have they been moved to Provisional or dropped?
15
16      - NA https://wiki.opendaylight.org/view/OpenDaylight_Lisp_Flow_Mapping:Oxygen_Release_Plan
17
18 2. Are all your inter-project dependencies resolved (i.e., have the other
19    projects you were counting on given you what you needed)? No new dependencies
20
21 3. Were there any project-specific deliverables planned for this milestone?
22    No
23
24 Karaf Features Defined:
25 -----------------------
26
27 1. Are all your project's features that are intended for release added to the
28    features.xml and checked into integration git repository? No
29
30    - In progress
31
32 2. List all top-level, user-facing, and stable Karaf features for your project.
33
34    - **odl-lispflowmapping-msmr**: This is the core feature that provides the Mapping
35      Services and include the LISP southbound plugin feature as well.
36
37 Documentation:
38 --------------
39
40 1. List the kinds of documentation you will provide including at least:
41
42    - User Guide
43    - Release Notes
44
45 2. Have you checked in a reStructuredText outline to the docs repository? Yes
46
47    - https://git.opendaylight.org/gerrit/gitweb?p=docs.git;a=blob;f=docs/user-guide/lisp-flow-mapping-user-guide.rst;h=db9419246f3e707f23c48d6ed965f11de7911c48;hb=HEAD
48
49 Integration and Test:
50 ---------------------
51
52 1. Have you started automated system testing for your top-level features? Yes
53
54    - https://jenkins.opendaylight.org/releng/view/lispflowmapping/job/lispflowmapping-csit-1node-msmr-all-oxygen/
55    - https://jenkins.opendaylight.org/releng/view/lispflowmapping/job/lispflowmapping-csit-1node-performance-only-oxygen/
56    - https://jenkins.opendaylight.org/releng/view/lispflowmapping/job/lispflowmapping-csit-3node-msmr-all-oxygen/
57
58 2. Have you filled out basic system test plan template for each top-level
59    feature (karaf and not karaf) and a comprehensive system test plan template
60    including functionality, cluster, scalability, performance,
61    longevity/stability for each stable feature? Yes
62
63    - https://wiki.opendaylight.org/view/OpenDaylight_Lisp_Flow_Mapping:Oxygen:All_Integration_System_Test
64
65 Project Specific:
66 -----------------
67
68 1. Were there any project-specific deliverables planned for this milestone?
69    No
70
71 2. Have you updated your project facts with the project type category? Yes
72
73 3. Do you acknowledge the changes to the RC Blocking Bug Policy [3]_? Yes
74
75 .. [1] Note that you can only reasonably hold a project to something if you
76        formally asked for it during the release planning process and the project
77        team members acknowledged that ask saying they would do it.
78 .. [2] Release notes must be updated prior to a major release. It is a good idea
79        to keep release notes as a living document when significant changes are