l2switch M3 readout
[docs.git] / docs / release-process / milestone-readouts / m3 / faas.rst
1 ====
2 FaaS
3 ====
4
5 1. Do you have any previously-incomplete items from prior milestone
6    readouts? No
7
8 2. Has your project achieved API freeze such that all externally accessible
9    Stable or Provisional APIs will not be modified after now? Yes
10
11 3. Do you have content in your project documentation? Yes
12
13 4. Has your project met the requirements to be included in Maven Central [2]_? No
14
15 5. Were project-specific deliverables planned for this milestone delivered
16    successfully? No Deliverables
17
18 6. Have you started automated system testing for your top-level features? No
19
20 7. Does your project use any ports, including for testing? Yes
21
22    - 6641, 6653
23    - If yes, have you updated the wiki [3]_ with all ports used? Yes
24
25 8. Does your project build successfully in Autorelease? Yes
26
27 .. [1] Provide a link to a gerrit search for patches modifying the files
28        defined as specifying the API. For example:
29        https://git.opendaylight.org/gerrit/#/q/file:%255Eopendaylight/md-sal/sal-binding-api/.%252B+status:merged+project:controller
30 .. [2] http://central.sonatype.org/pages/requirements.html