5 1. Do you have any previously-incomplete items from prior milestone
8 2. Has your project achieved API freeze such that all externally accessible
9 Stable or Provisional APIs will not be modified after now? Yes
11 3. Do you have content in your project documentation? Yes
13 4. Has your project met the requirements to be included in Maven Central [2]_?
16 5. Were project-specific deliverables planned for this milestone delivered
19 6. Have you started automated system testing for your top-level features? No
21 - Test plan is being drawn up for M4, features are system-tested by mdsal
22 and controller projects.
24 7. Does your project use any ports, including for testing? No.
26 8. Does your project build successfully in Autorelease? No
28 - yangtools follows normal project release and has already released its Oxygen
31 .. [1] Provide a link to a gerrit search for patches modifying the files
32 defined as specifying the API. For example:
33 https://git.opendaylight.org/gerrit/#/q/file:%255Eopendaylight/md-sal/sal-binding-api/.%252B+status:merged+project:controller
34 .. [2] http://central.sonatype.org/pages/requirements.html