5 OpenDaylight releases twice per year. The six-month cadence is designed to
6 synchronize OpenDaylight releases with OpenStack and OPNFV releases. Dates
7 are adjusted to match current resources and requirements from the current
8 OpenDaylight users. Dates are also adjusted when they conflict with holidays,
9 overlap with other releases or are otherwise problematic. Dates include the
10 release of both managed and self-managed projects.
11
12 .. list-table::
13    :widths: 20 20 20 20 20 40
14    :header-rows: 1
15    :stub-columns: 1
16
17    * - **Event**
18      - **Magnesium Dates**
19      - **Aluminium Dates**
20      - **Relative Dates**
21      - **Start-Relative Dates**
22      - **Description**
23
24    * - Release Start
25      - 2019-09-09
26      - 2020-03-16
27      - Start Date
28      - Start Date +0
29      - Declare Intention: Submit **Project_Plan** Jira item in TSC project.
30    * - Initial Checkpoint
31      - 2019-09-23
32      - 2020-03-30
33      - Start Date +2 weeks
34      - Start Date +2 weeks
35      - Initial Checkpoint. All Managed Projects must have completed
36        **Project_Plan** Jira items in TSC project.
37    * - Release Integrated Deadline
38      - 2019-10-07
39      - 2020-04-13
40      - Initial Checkpoint + 2 weeks
41      - Start Date +4 weeks
42      - Deadline for Release Integrated Projects (currently, ODLPARENT,
43        YANGTOOLS and MDSAL) to provide the desired version deliverables for
44        downstream Snapshot Integrated Projects to consume.
45    * - Version Bump
46      - 2019-10-08
47      - 2020-04-14
48      - Release Integrated Deadline + 1 day
49      - Start Date +4 weeks 1 day
50      - Prepare version bump patches and merge them in (RelEng team). Spend the
51        next 2 weeks to get green build for all MSI Projects and a healthy
52        distribution.
53    * - Version Bump Checkpoint
54      - 2019-10-21
55      - 2020-04-27
56      - Release Integrated Deadline + 2 weeks
57      - Start Date +6 weeks
58      - Check status of MSI Projects to see if we have green builds and a
59        healthy distribution. Revert the MRI deliverables if deemed necessary.
60    * - CSIT Checkpoint
61      - 2019-11-04
62      - 2020-05-11
63      - Version Bump Checkpoint + 2 weeks
64      - Start Date +8 weeks
65      - All Managed Release CSIT should be in good shape - get all MSI Projects'
66        CSIT results as they were before the version bump. This is the final
67        opportunity to revert the MRI deliverables if deemed necessary.
68    * - Middle Checkpoint
69      - 2020-01-06
70      - 2020-07-06
71      - CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
72      - Start Date +16 weeks (sometimes +2 weeks to avoid December holidays)
73      - Checkpoint for status of Managed Projects - especially Snapshot
74        Integrated Projects.
75    * - Code Freeze
76      - 2020-02-03
77      - 2020-08-03
78      - Middle Checkpoint + 4 weeks
79      - Start Date +20 weeks
80      - Code freeze for all Managed Projects - cut and lock release branch. Only
81        allow blocker bugfixes in release branch.
82    * - Final Checkpoint
83      - 2020-02-17
84      - 2020-08-17
85      - Code Freeze + 2 weeks
86      - Start Date +22 weeks
87      - Final Checkpoint for all Managed Projects.
88    * - Formal Release
89      - 2020-03-09 (actual 2020-03-19)
90      - 2020-09-17
91      - 6 months after Start Date
92      - Start Date +6 months
93      - Formal Release for Managed Projects. Self-managed projects usually are released a week later.
94    * - Service Release 1
95      - 2020-05-04 (actual release 2020-05-15)
96      - 2020-10-29
97      - 1.5 month after Formal Release
98      - Start Date +7.5 months
99      - Service Release 1 (SR1)
100    * - Service Release 2
101      - 2020-07-20
102      - 2020-12-30
103      - 3 months after SR1
104      - Start Date +10.5 months
105      - Service Release 2 (SR2)
106    * - Service Release 3
107      - 2020-11-16
108      - 2021-04-30
109      - 4 months after SR2
110      - Start Date +14 months
111      - Service Release 3 (SR3) - Final Service Release
112    * - Release End of Life
113      - 2021-03-08
114      - 2021-09-13
115      - 4 months after SR3
116      - Start Date +18 months
117      - End of Life - coincides with the Formal Release of the current release+2