1 ================
2 Release Schedule
3 ================
4
5 OpenDaylight releases twice per year. The six-month cadence is designed to
6 synchronize OpenDaylight releases with OpenStack and OPNFV releases. Dates
7 are adjusted to match current resources and requirements from the current
8 OpenDaylight users. Dates are also adjusted when they conflict with holidays,
9 overlap with other releases or are otherwise problematic. Dates include the
10 release of both managed and self-managed projects.
11
12 .. list-table::
13    :widths: 20 20 20 20 40
14    :header-rows: 1
15    :stub-columns: 1
16
17    * - **Event**
18      - **Magnesium Dates**
19      - **Relative Dates**
20      - **Start-Relative Dates**
21      - **Description**
22
23    * - Release Start
24      - 2019-09-09
25      - Start Date
26      - Start Date +0
27      - Declare Intention: Submit **Project_Plan** Jira item in TSC project.
28    * - Initial Checkpoint
29      - 2019-09-23
30      - Start Date +2 weeks
31      - Start Date +2 weeks
32      - Initial Checkpoint. All Managed Projects must have completed
33        **Project_Plan** Jira items in TSC project.
34    * - Release Integrated Deadline
35      - 2019-10-07
36      - Initial Checkpoint + 2 weeks
37      - Start Date +4 weeks
38      - Deadline for Release Integrated Projects (currently, ODLPARENT,
39        YANGTOOLS and MDSAL) to provide the desired version deliverables for
40        downstream Snapshot Integrated Projects to consume.
41    * - Version Bump
42      - 2019-10-08
43      - Release Integrated Deadline + 1 day
44      - Start Date +4 weeks 1 day
45      - Prepare version bump patches and merge them in (RelEng team). Spend the
46        next 2 weeks to get green build for all MSI Projects and a healthy
47        distribution.
48    * - Version Bump Checkpoint
49      - 2019-10-21
50      - Release Integrated Deadline + 2 weeks
51      - Start Date +6 weeks
52      - Check status of MSI Projects to see if we have green builds and a
53        healthy distribution. Revert the MRI deliverables if deemed necessary.
54    * - CSIT Checkpoint
55      - 2019-11-04
56      - Version Bump Checkpoint + 2 weeks
57      - Start Date +8 weeks
58      - All Managed Release CSIT should be in good shape - get all MSI Projects'
59        CSIT results as they were before the version bump. This is the final
60        opportunity to revert the MRI deliverables if deemed necessary.
61    * - Middle Checkpoint
62      - 2020-01-06
63      - CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
64      - Start Date +16 weeks (sometimes +2 weeks to avoid December holidays)
65      - Checkpoint for status of Managed Projects - especially Snapshot
66        Integrated Projects.
67    * - Code Freeze
68      - 2020-02-03
69      - Middle Checkpoint + 4 weeks
70      - Start Date +20 weeks
71      - Code freeze for all Managed Projects - cut and lock release branch. Only
72        allow blocker bugfixes in release branch.
73    * - Final Checkpoint
74      - 2020-02-17
75      - Code Freeze + 2 weeks
76      - Start Date +22 weeks
77      - Final Checkpoint for all Managed Projects.
78    * - Formal Release
79      - 2020-03-09 (actual 2020-03-19)
80      - 6 months after Start Date
81      - Start Date +6 months
82      - Formal Release for Managed Projects. Self-managed projects usually are released a week later.
83    * - Service Release 1
84      - 2020-05-04 (actual release 2020-05-15)
85      - 1.5 month after Formal Release
86      - Start Date +7.5 months
87      - Service Release 1 (SR1)
88    * - Service Release 2
89      - 2020-07-20
90      - 3 months after SR1
91      - Start Date +10.5 months
92      - Service Release 2 (SR2)
93    * - Service Release 3
94      - 2020-11-16
95      - 4 months after SR2
96      - Start Date +14 months
97      - Service Release 3 (SR3)
98    * - Service Release 4
99      - 2020-08-28
100      - Not Applicable
101      - Not Applicable
102      - Service Release 4 (SR4) - Final Service Release
103    * - Release End of Life
104      - 2021-03-08
105      - 4 months after SR3
106      - Start Date +18 months