-Release Schedule
-================
-
-The start date for odd release is September 7 and the start date for even
-release is March 7.
-
-.. list-table::
- :widths: 20 20 20 40
- :header-rows: 1
- :stub-columns: 1
-
- * - **Milestone**
- - **Time**
- - **Fluorine**
- - **Description**
-
- * - Release Start
- - Start Date
- - 2018-03-07
- - Declare Intention: Submit **Project_Plan** Jira item in TSC project
-
- * - Initial Checkpoint
- - Start Date + 2 weeks
- - 2018-03-22
- - Initial Checkpoint. All Managed Projects must have completed
- **Project_Plan** Jira items in TSC project.
-
- * - Release Integrated Deadline
- - Initial Checkpoint + 2 weeks
- - 2018-04-07
- - Deadline for Release Integrated Projects (currently ODLPARENT and
- YANGTOOLS) to provide the desired version deliverables for downstream
- Snapshot Integrated Projects to consume.
-
- * - Version Bump
- - Release Integrated Deadline + 1 day
- - 2018-04-08
- - Prepare version bump patches and merge them in (RelEng team). Spend the
- next 2 weeks to get green build for all MSI Projects and a healthy
- distribution.
-
- * - Version Bump Checkpoint
- - Release Integrated Deadline + 2 weeks
- - 2018-04-21
- - Check status of MSI Projects to see if we have green builds and a
- healthy distribution. Revert the MRI deliverables if deemed necessary.
-
- * - CSIT Checkpoint
- - Version Bump Checkpoint + 2 weeks
- - 2018-05-07
- - All Managed Release CSIT should be in good shape - get all MSI Projects'
- CSIT results as they were before the version bump. This is the final
- opportunity to revert the MRI deliverables if deemed necessary.
-
- * - Middle Checkpoint
- - CSIT Checkpoint + 8 weeks
- - 2018-07-05
- - Checkpoint for status of Managed Projects - especially Snapshot
- Integrated Projects.
-
- * - Code Freeze
- - Middle Checkpoint + 4 weeks
- - 2018-08-07
- - Code freeze for all Managed Projects - cut and lock release branch. Only
- allow blocker bugfixes in release branch.
-
- * - Final Checkpoint
- - TSC meeting 2 weeks after Code Freeze
- - 2018-08-23
- - Final Checkpoint for all Managed Projects.
-
- * - Formal Release
- - 6 months after Start Date
- - 2018-09-07
- - Formal release
-
- * - Service Release 1
- - 1 month after Formal Release
- - 2018-10-07
- - Service Release 1 (SR1)
-
- * - Service Release 2
- - 2 months after SR1
- - 2018-12-07
- - Service Release 2 (SR2)
-
- * - Service Release 3
- - 2 months after SR2
- - 2019-02-07
- - Service Release 3 (SR3)
-
- * - Service Release 4
- - 3 months after SR3
- - 2019-05-07
- - Service Release 4 (SR4) - final service release
-
- * - Release End of Life
- - 4 months after SR4
- - 2019-09-07
- - End of Life - coincides with the Formal Release of the current release+2
- versions and the start of the current release+3 versions
-