now that Silicon is released.
JIRA: TSC-305
Signed-off-by: Guillaume Lambert <guillaume.lambert@orange.com>
Change-Id: I6f7e01bb2c74bd0c68d17cd7382acd58f60d2af4
:stub-columns: 1
* - **Event**
:stub-columns: 1
* - **Event**
- **Relative Dates**
- **Start-Relative Dates**
- **Description**
* - Release Start
- **Relative Dates**
- **Start-Relative Dates**
- **Description**
* - Release Start
- Start Date
- Start Date +0
- Declare Intention: Submit **Project_Plan** Jira item in TSC project.
* - Initial Checkpoint
- Start Date
- Start Date +0
- Declare Intention: Submit **Project_Plan** Jira item in TSC project.
* - Initial Checkpoint
- Start Date +2 weeks
- Start Date +2 weeks
- Initial Checkpoint. All Managed Projects must have completed
**Project_Plan** Jira items in TSC project.
* - Release Integrated Deadline
- Start Date +2 weeks
- Start Date +2 weeks
- Initial Checkpoint. All Managed Projects must have completed
**Project_Plan** Jira items in TSC project.
* - Release Integrated Deadline
- Initial Checkpoint + 2 weeks
- Start Date +4 weeks
- Deadline for Release Integrated Projects (currently, ODLPARENT,
- Initial Checkpoint + 2 weeks
- Start Date +4 weeks
- Deadline for Release Integrated Projects (currently, ODLPARENT,
version deliverables for downstream Snapshot Integrated Projects to
consume.
* - Version Bump
version deliverables for downstream Snapshot Integrated Projects to
consume.
* - Version Bump
- Release Integrated Deadline + 1 day
- Start Date +4 weeks 1 day
- Prepare version bump patches and merge them in (RelEng team). Spend the
next 2 weeks to get green build for all MSI Projects and a healthy
distribution.
* - Version Bump Checkpoint
- Release Integrated Deadline + 1 day
- Start Date +4 weeks 1 day
- Prepare version bump patches and merge them in (RelEng team). Spend the
next 2 weeks to get green build for all MSI Projects and a healthy
distribution.
* - Version Bump Checkpoint
- Release Integrated Deadline + 2 weeks
- Start Date +6 weeks
- Check status of MSI Projects to see if we have green builds and a
healthy distribution. Revert the MRI deliverables if deemed necessary.
* - CSIT Checkpoint
- Release Integrated Deadline + 2 weeks
- Start Date +6 weeks
- Check status of MSI Projects to see if we have green builds and a
healthy distribution. Revert the MRI deliverables if deemed necessary.
* - CSIT Checkpoint
- Version Bump Checkpoint + 2 weeks
- Start Date +8 weeks
- All Managed Release CSIT should be in good shape - get all MSI Projects'
CSIT results as they were before the version bump. This is the final
opportunity to revert the MRI deliverables if deemed necessary.
* - Middle Checkpoint
- Version Bump Checkpoint + 2 weeks
- Start Date +8 weeks
- All Managed Release CSIT should be in good shape - get all MSI Projects'
CSIT results as they were before the version bump. This is the final
opportunity to revert the MRI deliverables if deemed necessary.
* - Middle Checkpoint
- CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
- Start Date +16 weeks (sometimes +2 weeks to avoid December holidays)
- Checkpoint for status of Managed Projects - especially Snapshot
Integrated Projects.
* - Code Freeze
- CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
- Start Date +16 weeks (sometimes +2 weeks to avoid December holidays)
- Checkpoint for status of Managed Projects - especially Snapshot
Integrated Projects.
* - Code Freeze
- Middle Checkpoint + 4 weeks
- Start Date +20 weeks
- Code freeze for all Managed Projects - cut and lock release branch. Only
allow blocker bugfixes in release branch.
* - Final Checkpoint
- Middle Checkpoint + 4 weeks
- Start Date +20 weeks
- Code freeze for all Managed Projects - cut and lock release branch. Only
allow blocker bugfixes in release branch.
* - Final Checkpoint
- Code Freeze + 2 weeks
- Start Date +22 weeks
- Final Checkpoint for all Managed Projects.
* - Formal Release
- Code Freeze + 2 weeks
- Start Date +22 weeks
- Final Checkpoint for all Managed Projects.
* - Formal Release
- 6 months after Start Date
- Start Date +6 months
- Formal Release for Managed Projects. Self-managed projects usually are released a week later.
* - Service Release 1
- 6 months after Start Date
- Start Date +6 months
- Formal Release for Managed Projects. Self-managed projects usually are released a week later.
* - Service Release 1
- 1.5 month after Formal Release
- Start Date +7.5 months
- Service Release 1 (SR1)
* - Service Release 2
- 1.5 month after Formal Release
- Start Date +7.5 months
- Service Release 1 (SR1)
* - Service Release 2
- 3 months after SR1
- Start Date +10.5 months
- Service Release 2 (SR2)
* - Service Release 3
- 3 months after SR1
- Start Date +10.5 months
- Service Release 2 (SR2)
* - Service Release 3
- 4 months after SR2
- Start Date +14 months
- Service Release 3 (SR3)
- 4 months after SR2
- Start Date +14 months
- Service Release 3 (SR3)
- Not Applicable
- Service Release 4 (SR4) - Final Service Release
* - Release End of Life
- Not Applicable
- Service Release 4 (SR4) - Final Service Release
* - Release End of Life
- 4 months after SR3
- Start Date +18 months
- End of Life - coincides with the Formal Release of the current release+2
- 4 months after SR3
- Start Date +18 months
- End of Life - coincides with the Formal Release of the current release+2