:stub-columns: 1
* - **Event**
+ - **Chlorine Dates**
- **Sulfur Dates**
- **Phosphorus Dates**
- - **Silicon Dates**
- **Relative Dates**
- **Start-Relative Dates**
- **Description**
* - Release Start
+ - 2022-03-17
- 2021-09-23
- 2021-03-17
- - 2020-09-17
- Start Date
- Start Date +0
- Declare Intention: Submit **Project_Plan** Jira item in TSC project.
* - Initial Checkpoint
+ - 2022-03-31
- 2021-10-07
- 2021-03-31
- - 2020-10-01
- Start Date +2 weeks
- Start Date +2 weeks
- Initial Checkpoint. All Managed Projects must have completed
**Project_Plan** Jira items in TSC project.
* - Release Integrated Deadline
+ - 2022-04-14
- 2021-10-21
- 2021-04-15
- - 2020-10-15
- Initial Checkpoint + 2 weeks
- Start Date +4 weeks
- Deadline for Release Integrated Projects (currently, ODLPARENT,
version deliverables for downstream Snapshot Integrated Projects to
consume.
* - Version Bump
+ - 2022-04-15
- 2021-10-22
- 2021-04-16
- - 2020-10-16
- Release Integrated Deadline + 1 day
- Start Date +4 weeks 1 day
- Prepare version bump patches and merge them in (RelEng team). Spend the
next 2 weeks to get green build for all MSI Projects and a healthy
distribution.
* - Version Bump Checkpoint
+ - 2022-04-29
- 2021-11-04
- 2021-04-29
- - 2020-10-29
- Release Integrated Deadline + 2 weeks
- Start Date +6 weeks
- Check status of MSI Projects to see if we have green builds and a
healthy distribution. Revert the MRI deliverables if deemed necessary.
* - CSIT Checkpoint
+ - 2022-05-13
- 2021-11-18
- 2021-05-13
- - 2020-11-12
- Version Bump Checkpoint + 2 weeks
- Start Date +8 weeks
- All Managed Release CSIT should be in good shape - get all MSI Projects'
CSIT results as they were before the version bump. This is the final
opportunity to revert the MRI deliverables if deemed necessary.
* - Middle Checkpoint
+ - 2022-07-07
- 2022-01-13
- 2021-07-08
- - 2021-01-07
- CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
- Start Date +16 weeks (sometimes +2 weeks to avoid December holidays)
- Checkpoint for status of Managed Projects - especially Snapshot
Integrated Projects.
* - Code Freeze
+ - 2022-08-04
- 2022-02-10
- 2021-08-05
- - 2021-02-22
- Middle Checkpoint + 4 weeks
- Start Date +20 weeks
- Code freeze for all Managed Projects - cut and lock release branch. Only
allow blocker bug fixes in release branch.
* - Final Checkpoint
+ - 2022-08-19
- 2022-02-24
- 2021-08-19
- - 2021-03-08
- Code Freeze + 2 weeks
- Start Date +22 weeks
- Final Checkpoint for all Managed Projects.
* - Formal Release
+ - 2022-09-19
- 2022-03-17
- 2021-09-16
- - 2021-03-17
- 6 months after Start Date
- Start Date +6 months
- Formal Release for Managed Projects. Self-managed projects usually are released a week later.
* - Service Release 1
+ - 2022-10-24
- 2022-04-28
- 2021-11-22
- - 2021-06-03
- 1.5 month after Formal Release
- Start Date +7.5 months
- Service Release 1 (SR1)
* - Service Release 2
+ - 2023-01-23
- 2022-07-28
- 2022-01-27
- - 2021-07-28
- 3 months after SR1
- Start Date +10.5 months
- Service Release 2 (SR2)
* - Service Release 3
+ - 2023-05-08
- 2022-10-28
- 2022-05-12
- - 2021-11-04
- 4 months after SR2
- Start Date +14 months
- Service Release 3 (SR3)
- Not Applicable
- Service Release 4 (SR4) - Final Service Release
* - Release End of Life
+ - 2023-09-19
- 2023-03-16
- 2022-09-15
- - 2022-03-17
- 4 months after SR3
- Start Date +18 months
- End of Life - coincides with the Formal Release of the current release+2