Update release schedule for Sulfur, P SR1 & Si SR3 91/97991/1
authorguillaume.lambert <guillaume.lambert@orange.com>
Tue, 19 Oct 2021 18:16:44 +0000 (20:16 +0200)
committerguillaume.lambert <guillaume.lambert@orange.com>
Tue, 19 Oct 2021 18:17:29 +0000 (20:17 +0200)
Signed-off-by: guillaume.lambert <guillaume.lambert@orange.com>
Change-Id: I06c2166dbe2f7e90f3dd202db6a0b833a119ef6a

docs/release-process/release-schedule.rst

index 121eb5b8b33cc99ff282aa5968babc272d752dad..5e2a4cf71d24943dfb9aaba6b3f678fc0b80e83b 100644 (file)
@@ -12,11 +12,12 @@ Self-managed projects that wants to integrate the distribution have one week
 to release once managed projects are ready.
 
 .. list-table::
-   :widths: 20 20 20 20 20 40
+   :widths: 20 20 20 20 20 20 40
    :header-rows: 1
    :stub-columns: 1
 
    * - **Event**
+     - **Sulfur Dates**
      - **Phosphorus Dates**
      - **Silicon Dates**
      - **Relative Dates**
@@ -24,12 +25,14 @@ to release once managed projects are ready.
      - **Description**
 
    * - Release Start
+     - 2021-09-23
      - 2021-03-17
      - 2020-09-17
      - Start Date
      - Start Date +0
      - Declare Intention: Submit **Project_Plan** Jira item in TSC project.
    * - Initial Checkpoint
+     - 2021-10-07
      - 2021-03-31
      - 2020-10-01
      - Start Date +2 weeks
@@ -37,6 +40,7 @@ to release once managed projects are ready.
      - Initial Checkpoint. All Managed Projects must have completed
        **Project_Plan** Jira items in TSC project.
    * - Release Integrated Deadline
+     - 2021-10-21
      - 2021-04-15
      - 2020-10-15
      - Initial Checkpoint + 2 weeks
@@ -46,6 +50,7 @@ to release once managed projects are ready.
        version deliverables for downstream Snapshot Integrated Projects to
        consume.
    * - Version Bump
+     - 2021-10-22
      - 2021-04-16
      - 2020-10-16
      - Release Integrated Deadline + 1 day
@@ -54,6 +59,7 @@ to release once managed projects are ready.
        next 2 weeks to get green build for all MSI Projects and a healthy
        distribution.
    * - Version Bump Checkpoint
+     - 2021-11-04
      - 2021-04-29
      - 2020-10-29
      - Release Integrated Deadline + 2 weeks
@@ -61,6 +67,7 @@ to release once managed projects are ready.
      - Check status of MSI Projects to see if we have green builds and a
        healthy distribution. Revert the MRI deliverables if deemed necessary.
    * - CSIT Checkpoint
+     - 2021-11-18
      - 2021-05-13
      - 2020-11-12
      - Version Bump Checkpoint + 2 weeks
@@ -69,6 +76,7 @@ to release once managed projects are ready.
        CSIT results as they were before the version bump. This is the final
        opportunity to revert the MRI deliverables if deemed necessary.
    * - Middle Checkpoint
+     - 2022-01-13
      - 2021-07-08
      - 2021-01-07
      - CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
@@ -76,6 +84,7 @@ to release once managed projects are ready.
      - Checkpoint for status of Managed Projects - especially Snapshot
        Integrated Projects.
    * - Code Freeze
+     - 2022-02-10
      - 2021-08-05
      - 2021-02-22
      - Middle Checkpoint + 4 weeks
@@ -83,42 +92,49 @@ to release once managed projects are ready.
      - Code freeze for all Managed Projects - cut and lock release branch. Only
        allow blocker bug fixes in release branch.
    * - Final Checkpoint
+     - 2022-02-24
      - 2021-08-19
      - 2021-03-08
      - Code Freeze + 2 weeks
      - Start Date +22 weeks
      - Final Checkpoint for all Managed Projects.
    * - Formal Release
+     - 2022-03-17
      - 2021-09-16
      - 2021-03-17
      - 6 months after Start Date
      - Start Date +6 months
      - Formal Release for Managed Projects. Self-managed projects usually are released a week later.
    * - Service Release 1
-     - 2021-10-28
+     - 2022-04-28
+     - 2021-11-22
      - 2021-06-03
      - 1.5 month after Formal Release
      - Start Date +7.5 months
      - Service Release 1 (SR1)
    * - Service Release 2
+     - 2022-07-28
      - 2022-01-27
      - 2021-07-28
      - 3 months after SR1
      - Start Date +10.5 months
      - Service Release 2 (SR2)
    * - Service Release 3
+     - 2022-10-28
      - 2022-05-12
-     - 2021-10-28
+     - 2021-11-04
      - 4 months after SR2
      - Start Date +14 months
      - Service Release 3 (SR3)
    * - Service Release 4
+     - N/A
      - N/A
      - N/A
      - Not Applicable
      - Not Applicable
      - Service Release 4 (SR4) - Final Service Release
    * - Release End of Life
+     - 2023-03-16
      - 2022-09-15
      - 2022-03-17
      - 4 months after SR3