Update Magnesium release schedule 79/88879/1
authorDavid Baugher <dbaugher@luminanetworks.com>
Fri, 3 Apr 2020 17:13:06 +0000 (10:13 -0700)
committerDavid Baugher <dbaugher@luminanetworks.com>
Fri, 3 Apr 2020 17:13:06 +0000 (10:13 -0700)
Signed-off-by: David Baugher <dbaugher@luminanetworks.com>
Change-Id: Ice9c103d93fc07b08e46d601e7b842dd97cf749a

docs/release-process/release-schedule.rst

index 500569df62bb36d1d332f36e0ab8e269561cd5d4..94c5e9ce633c124c9072112e4638ed8e2ac3f2fa 100644 (file)
@@ -42,7 +42,6 @@ release of both managed and self-managed projects.
      - Deadline for Release Integrated Projects (currently, ODLPARENT,
        YANGTOOLS and MDSAL) to provide the desired version deliverables for
        downstream Snapshot Integrated Projects to consume.
-       For Sodium, this is +1 more week to resolve conflict with ONS NA 2019.
    * - Version Bump
      - 2019-10-08
      - 2020-04-14
@@ -93,7 +92,7 @@ release of both managed and self-managed projects.
      - Start Date +6 months
      - Formal Release for Managed Projects. Self-managed projects usually are released a week later.
    * - Service Release 1
-     - 2020-04-20
+     - 2020-05-04
      - 2020-10-29
      - 1.5 month after Formal Release
      - Start Date +7.5 months