problematic.
.. list-table::
- :widths: 20 20 20 20 20 40
+ :widths: 20 20 20 20 20 20 40
:header-rows: 1
:stub-columns: 1
* - **Event**
- **Fluorine Date**
- **Neon Date**
+ - **Sodium Date**
- **Relative Date**
- **Start-Relative Date**
- **Description**
* - Release Start
- 2018-03-07
- 2018-09-06
+ - 2019-03-07
- Start Date
- Start Date +0
- Declare Intention: Submit **Project_Plan** Jira item in TSC project
* - Initial Checkpoint
- 2018-03-22
- 2018-09-20
+ - 2019-03-21
- Start Date + 2 weeks
- Start Date +2 weeks
- Initial Checkpoint. All Managed Projects must have completed
* - Release Integrated Deadline
- 2018-04-07
- 2018-10-04
+ - 2019-04-11
- Initial Checkpoint + 2 weeks
- Start Date +4 weeks
- Deadline for Release Integrated Projects (currently ODLPARENT,
YANGTOOLS and MDSAL) to provide the desired version deliverables for
downstream Snapshot Integrated Projects to consume.
+ For Sodium, this is +1 more week to resolve conflict with ONS NA 2019.
* - Version Bump
- 2018-04-08
- 2018-10-05
+ - 2019-04-12
- Release Integrated Deadline + 1 day
- Start Date +4 weeks 1 day
- Prepare version bump patches and merge them in (RelEng team). Spend the
* - Version Bump Checkpoint
- 2018-04-21
- 2018-10-18
+ - 2019-04-25
- Release Integrated Deadline + 2 weeks
- Start Date +6 weeks
- Check status of MSI Projects to see if we have green builds and a
* - CSIT Checkpoint
- 2018-05-07
- 2018-11-01
+ - 2019-05-09
- Version Bump Checkpoint + 2 weeks
- Start Date +8 weeks
- All Managed Release CSIT should be in good shape - get all MSI Projects'
* - Middle Checkpoint
- 2018-07-05
- 2019-01-10
- - CSIT Checkpoint + 8 weeks (+2 weeks to avoid holidays)
- - Start Date +16 weeks (+2 weeks to avoid holidays)
+ - 2019-07-04
+ - CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
+ - Start Date +16 weeks (sometimes +2 weeks to avoid December holidays)
- Checkpoint for status of Managed Projects - especially Snapshot
Integrated Projects.
* - Code Freeze
- 2018-08-07
- 2019-01-24
+ - 2019-08-01
- Middle Checkpoint + 4 weeks
- Start Date +20 weeks
- Code freeze for all Managed Projects - cut and lock release branch. Only
* - Final Checkpoint
- 2018-08-23
- 2019-02-07
+ - 2019-08-15
- Code Freeze + 2 weeks
- Start Date +22 weeks
- Final Checkpoint for all Managed Projects.
* - Formal Release
- 2018-09-07
- 2019-03-06
+ - 2019-09-05
- 6 months after Start Date
- Start Date +6 months
- Formal release
* - Service Release 1
- 2018-10-07
- 2019-04-06
+ - 2019-10-03
- 1 month after Formal Release
- Start Date +7 months
- Service Release 1 (SR1)
* - Service Release 2
- 2018-12-07
- 2019-06-06
+ - 2019-12-05
- 2 months after SR1
- Start Date +9 months
- Service Release 2 (SR2)
* - Service Release 3
- 2019-02-07
- 2019-08-06
+ - 2020-02-06
- 2 months after SR2
- Start Date +11 months
- Service Release 3 (SR3)
* - Service Release 4
- 2019-05-07
- 2019-11-06
+ - 2020-05-07
- 3 months after SR3
- Start Date +14 months
- Service Release 4 (SR4) - final service release
* - Release End of Life
- 2019-09-07
- 2020-03-06
+ - 2020-09-03
- 4 months after SR4
- Start Date +18 months
- End of Life - coincides with the Formal Release of the current release+2