From: Guillaume Lambert Date: Wed, 31 Mar 2021 10:02:53 +0000 (+0200) Subject: Update Release Schedule for Phosphorus X-Git-Url: https://git.opendaylight.org/gerrit/gitweb?a=commitdiff_plain;h=e36028aed23c000c12d62b99960da1b9d72da19f;p=docs.git Update Release Schedule for Phosphorus now that Silicon is released. JIRA: TSC-305 Signed-off-by: Guillaume Lambert Change-Id: I6f7e01bb2c74bd0c68d17cd7382acd58f60d2af4 --- diff --git a/docs/release-process/release-schedule.rst b/docs/release-process/release-schedule.rst index b7a67e8a4..51f95db3c 100644 --- a/docs/release-process/release-schedule.rst +++ b/docs/release-process/release-schedule.rst @@ -17,28 +17,28 @@ to release once managed projects are ready. :stub-columns: 1 * - **Event** + - **Phosphorus Dates** - **Silicon Dates** - - **Aluminium Dates** - **Relative Dates** - **Start-Relative Dates** - **Description** * - Release Start + - 2021-03-17 - 2020-09-17 - - 2020-03-16 - Start Date - Start Date +0 - Declare Intention: Submit **Project_Plan** Jira item in TSC project. * - Initial Checkpoint + - 2021-03-31 - 2020-10-01 - - 2020-03-30 - Start Date +2 weeks - Start Date +2 weeks - Initial Checkpoint. All Managed Projects must have completed **Project_Plan** Jira items in TSC project. * - Release Integrated Deadline + - 2021-04-15 - 2020-10-15 - - 2020-04-13 - Initial Checkpoint + 2 weeks - Start Date +4 weeks - Deadline for Release Integrated Projects (currently, ODLPARENT, @@ -46,69 +46,69 @@ to release once managed projects are ready. version deliverables for downstream Snapshot Integrated Projects to consume. * - Version Bump + - 2021-04-16 - 2020-10-16 - - 2020-04-14 - Release Integrated Deadline + 1 day - Start Date +4 weeks 1 day - Prepare version bump patches and merge them in (RelEng team). Spend the next 2 weeks to get green build for all MSI Projects and a healthy distribution. * - Version Bump Checkpoint + - 2021-04-29 - 2020-10-29 - - 2020-04-27 - Release Integrated Deadline + 2 weeks - Start Date +6 weeks - Check status of MSI Projects to see if we have green builds and a healthy distribution. Revert the MRI deliverables if deemed necessary. * - CSIT Checkpoint + - 2021-05-13 - 2020-11-12 - - 2020-05-11 - Version Bump Checkpoint + 2 weeks - Start Date +8 weeks - All Managed Release CSIT should be in good shape - get all MSI Projects' CSIT results as they were before the version bump. This is the final opportunity to revert the MRI deliverables if deemed necessary. * - Middle Checkpoint + - 2021-07-08 - 2021-01-07 - - 2020-07-06 - CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays) - Start Date +16 weeks (sometimes +2 weeks to avoid December holidays) - Checkpoint for status of Managed Projects - especially Snapshot Integrated Projects. * - Code Freeze + - 2021-08-05 - 2021-02-22 - - 2020-08-03 - Middle Checkpoint + 4 weeks - Start Date +20 weeks - Code freeze for all Managed Projects - cut and lock release branch. Only allow blocker bugfixes in release branch. * - Final Checkpoint + - 2021-08-19 - 2021-03-08 - - 2020-08-17 - Code Freeze + 2 weeks - Start Date +22 weeks - Final Checkpoint for all Managed Projects. * - Formal Release + - 2021-09-16 - 2021-03-17 - - 2020-09-17 - 6 months after Start Date - Start Date +6 months - Formal Release for Managed Projects. Self-managed projects usually are released a week later. * - Service Release 1 + - 2021-10-28 - 2021-04-28 - - 2020-10-29 - 1.5 month after Formal Release - Start Date +7.5 months - Service Release 1 (SR1) * - Service Release 2 + - 2022-01-27 - 2021-07-28 - - 2020-12-30 - 3 months after SR1 - Start Date +10.5 months - Service Release 2 (SR2) * - Service Release 3 + - 2022-05-12 - 2021-10-28 - - 2021-04-30 - 4 months after SR2 - Start Date +14 months - Service Release 3 (SR3) @@ -119,8 +119,8 @@ to release once managed projects are ready. - Not Applicable - Service Release 4 (SR4) - Final Service Release * - Release End of Life + - 2022-09-15 - 2022-03-17 - - 2021-09-13 - 4 months after SR3 - Start Date +18 months - End of Life - coincides with the Formal Release of the current release+2