From 92581c2859856869ef20d27c5873a33c58a5328b Mon Sep 17 00:00:00 2001 From: "guillaume.lambert" Date: Tue, 19 Oct 2021 20:16:44 +0200 Subject: [PATCH] Update release schedule for Sulfur, P SR1 & Si SR3 Signed-off-by: guillaume.lambert Change-Id: I06c2166dbe2f7e90f3dd202db6a0b833a119ef6a (cherry picked from commit 843d91aacd0abe4b9ee3655a72bbae0de0c93f30) --- docs/release-process/release-schedule.rst | 52 +++++++++++++++-------- 1 file changed, 34 insertions(+), 18 deletions(-) diff --git a/docs/release-process/release-schedule.rst b/docs/release-process/release-schedule.rst index 13b11bd5c..5e2a4cf71 100644 --- a/docs/release-process/release-schedule.rst +++ b/docs/release-process/release-schedule.rst @@ -12,33 +12,37 @@ Self-managed projects that wants to integrate the distribution have one week to release once managed projects are ready. .. list-table:: - :widths: 20 20 20 20 20 40 + :widths: 20 20 20 20 20 20 40 :header-rows: 1 :stub-columns: 1 * - **Event** + - **Sulfur Dates** + - **Phosphorus Dates** - **Silicon Dates** - - **Aluminium Dates** - **Relative Dates** - **Start-Relative Dates** - **Description** * - Release Start + - 2021-09-23 + - 2021-03-17 - 2020-09-17 - - 2020-03-16 - Start Date - Start Date +0 - Declare Intention: Submit **Project_Plan** Jira item in TSC project. * - Initial Checkpoint + - 2021-10-07 + - 2021-03-31 - 2020-10-01 - - 2020-03-30 - Start Date +2 weeks - Start Date +2 weeks - Initial Checkpoint. All Managed Projects must have completed **Project_Plan** Jira items in TSC project. * - Release Integrated Deadline + - 2021-10-21 + - 2021-04-15 - 2020-10-15 - - 2020-04-13 - Initial Checkpoint + 2 weeks - Start Date +4 weeks - Deadline for Release Integrated Projects (currently, ODLPARENT, @@ -46,81 +50,93 @@ to release once managed projects are ready. version deliverables for downstream Snapshot Integrated Projects to consume. * - Version Bump + - 2021-10-22 + - 2021-04-16 - 2020-10-16 - - 2020-04-14 - Release Integrated Deadline + 1 day - Start Date +4 weeks 1 day - Prepare version bump patches and merge them in (RelEng team). Spend the next 2 weeks to get green build for all MSI Projects and a healthy distribution. * - Version Bump Checkpoint + - 2021-11-04 + - 2021-04-29 - 2020-10-29 - - 2020-04-27 - Release Integrated Deadline + 2 weeks - Start Date +6 weeks - Check status of MSI Projects to see if we have green builds and a healthy distribution. Revert the MRI deliverables if deemed necessary. * - CSIT Checkpoint + - 2021-11-18 + - 2021-05-13 - 2020-11-12 - - 2020-05-11 - Version Bump Checkpoint + 2 weeks - Start Date +8 weeks - All Managed Release CSIT should be in good shape - get all MSI Projects' CSIT results as they were before the version bump. This is the final opportunity to revert the MRI deliverables if deemed necessary. * - Middle Checkpoint + - 2022-01-13 + - 2021-07-08 - 2021-01-07 - - 2020-07-06 - CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays) - Start Date +16 weeks (sometimes +2 weeks to avoid December holidays) - Checkpoint for status of Managed Projects - especially Snapshot Integrated Projects. * - Code Freeze + - 2022-02-10 + - 2021-08-05 - 2021-02-22 - - 2020-08-03 - Middle Checkpoint + 4 weeks - Start Date +20 weeks - Code freeze for all Managed Projects - cut and lock release branch. Only allow blocker bug fixes in release branch. * - Final Checkpoint + - 2022-02-24 + - 2021-08-19 - 2021-03-08 - - 2020-08-17 - Code Freeze + 2 weeks - Start Date +22 weeks - Final Checkpoint for all Managed Projects. * - Formal Release + - 2022-03-17 + - 2021-09-16 - 2021-03-17 - - 2020-09-17 - 6 months after Start Date - Start Date +6 months - Formal Release for Managed Projects. Self-managed projects usually are released a week later. * - Service Release 1 + - 2022-04-28 + - 2021-11-22 - 2021-06-03 - - 2020-10-29 - 1.5 month after Formal Release - Start Date +7.5 months - Service Release 1 (SR1) * - Service Release 2 + - 2022-07-28 + - 2022-01-27 - 2021-07-28 - - N/A - 3 months after SR1 - Start Date +10.5 months - Service Release 2 (SR2) * - Service Release 3 - - 2021-10-28 - - 2021-03-19 + - 2022-10-28 + - 2022-05-12 + - 2021-11-04 - 4 months after SR2 - Start Date +14 months - Service Release 3 (SR3) * - Service Release 4 - N/A - - 2021-06-02 + - N/A + - N/A - Not Applicable - Not Applicable - Service Release 4 (SR4) - Final Service Release * - Release End of Life + - 2023-03-16 + - 2022-09-15 - 2022-03-17 - - 2021-09-13 - 4 months after SR3 - Start Date +18 months - End of Life - coincides with the Formal Release of the current release+2 -- 2.36.6