Remove Aluminium from Magnesium schedule 18/92618/2
authorThanh Ha <zxiiro@gmail.com>
Wed, 23 Sep 2020 16:35:35 +0000 (12:35 -0400)
committerThanh Ha <zxiiro@gmail.com>
Wed, 23 Sep 2020 16:38:33 +0000 (12:38 -0400)
Signed-off-by: Thanh Ha <zxiiro@gmail.com>
Change-Id: Ic545cb3a3def699e6cd55a674beacf8a62e45f25

docs/release-process/release-schedule.rst

index afc36cd80dd1ba8efab1d69ffe7f6e0eea78603a..423f9323d7f869d55ccf8a4a92505fa8f0802bd8 100644 (file)
@@ -10,33 +10,29 @@ overlap with other releases or are otherwise problematic. Dates include the
 release of both managed and self-managed projects.
 
 .. list-table::
-   :widths: 20 20 20 20 20 40
+   :widths: 20 20 20 20 40
    :header-rows: 1
    :stub-columns: 1
 
    * - **Event**
      - **Magnesium Dates**
-     - **Aluminium Dates**
      - **Relative Dates**
      - **Start-Relative Dates**
      - **Description**
 
    * - Release Start
      - 2019-09-09
-     - 2020-03-16
      - Start Date
      - Start Date +0
      - Declare Intention: Submit **Project_Plan** Jira item in TSC project.
    * - Initial Checkpoint
      - 2019-09-23
-     - 2020-03-30
      - Start Date +2 weeks
      - Start Date +2 weeks
      - Initial Checkpoint. All Managed Projects must have completed
        **Project_Plan** Jira items in TSC project.
    * - Release Integrated Deadline
      - 2019-10-07
-     - 2020-04-13
      - Initial Checkpoint + 2 weeks
      - Start Date +4 weeks
      - Deadline for Release Integrated Projects (currently, ODLPARENT,
@@ -44,7 +40,6 @@ release of both managed and self-managed projects.
        downstream Snapshot Integrated Projects to consume.
    * - Version Bump
      - 2019-10-08
-     - 2020-04-14
      - Release Integrated Deadline + 1 day
      - Start Date +4 weeks 1 day
      - Prepare version bump patches and merge them in (RelEng team). Spend the
@@ -52,14 +47,12 @@ release of both managed and self-managed projects.
        distribution.
    * - Version Bump Checkpoint
      - 2019-10-21
-     - 2020-04-27
      - Release Integrated Deadline + 2 weeks
      - Start Date +6 weeks
      - Check status of MSI Projects to see if we have green builds and a
        healthy distribution. Revert the MRI deliverables if deemed necessary.
    * - CSIT Checkpoint
      - 2019-11-04
-     - 2020-05-11
      - Version Bump Checkpoint + 2 weeks
      - Start Date +8 weeks
      - All Managed Release CSIT should be in good shape - get all MSI Projects'
@@ -67,57 +60,48 @@ release of both managed and self-managed projects.
        opportunity to revert the MRI deliverables if deemed necessary.
    * - Middle Checkpoint
      - 2020-01-06
-     - 2020-07-06
      - CSIT Checkpoint + 8 weeks (sometimes +2 weeks to avoid December holidays)
      - Start Date +16 weeks (sometimes +2 weeks to avoid December holidays)
      - Checkpoint for status of Managed Projects - especially Snapshot
        Integrated Projects.
    * - Code Freeze
      - 2020-02-03
-     - 2020-08-03
      - Middle Checkpoint + 4 weeks
      - Start Date +20 weeks
      - Code freeze for all Managed Projects - cut and lock release branch. Only
        allow blocker bugfixes in release branch.
    * - Final Checkpoint
      - 2020-02-17
-     - 2020-08-17
      - Code Freeze + 2 weeks
      - Start Date +22 weeks
      - Final Checkpoint for all Managed Projects.
    * - Formal Release
      - 2020-03-09 (actual 2020-03-19)
-     - 2020-09-17
      - 6 months after Start Date
      - Start Date +6 months
      - Formal Release for Managed Projects. Self-managed projects usually are released a week later.
    * - Service Release 1
      - 2020-05-04 (actual release 2020-05-15)
-     - 2020-10-29
      - 1.5 month after Formal Release
      - Start Date +7.5 months
      - Service Release 1 (SR1)
    * - Service Release 2
      - 2020-07-20
-     - 2020-12-30
      - 3 months after SR1
      - Start Date +10.5 months
      - Service Release 2 (SR2)
    * - Service Release 3
      - 2020-11-16
-     - 2021-04-30
      - 4 months after SR2
      - Start Date +14 months
      - Service Release 3 (SR3)
    * - Service Release 4
      - 2020-08-28
-     - N/A
      - Not Applicable
      - Not Applicable
      - Service Release 4 (SR4) - Final Service Release
    * - Release End of Life
      - 2021-03-08
-     - 2021-09-13
      - 4 months after SR3
      - Start Date +18 months
      - End of Life - coincides with the Formal Release of the current release+2