Update the release and service release dates on the Magnesium page 19/89919/5
authorDavid Baugher <dbaugher@luminanetworks.com>
Fri, 22 May 2020 22:38:14 +0000 (15:38 -0700)
committerJamo Luhrsen <jluhrsen@gmail.com>
Sat, 23 May 2020 02:03:00 +0000 (02:03 +0000)
Signed-off-by: David Baugher <dbaugher@luminanetworks.com>
Change-Id: I224f18876381301cd950163a6d04d36ae87732d5

docs/release-process/release-schedule.rst

index 8bc636a5740e23501a2cf312ce0cd809aeb77c23..0667242fe97298ac417b30d6382af7e077ecfa6c 100644 (file)
@@ -86,13 +86,13 @@ release of both managed and self-managed projects.
      - Start Date +22 weeks
      - Final Checkpoint for all Managed Projects.
    * - Formal Release
-     - 2020-03-09
+     - 2020-03-09 (actual 2020-03-19)
      - 2020-09-17
      - 6 months after Start Date
      - Start Date +6 months
      - Formal Release for Managed Projects. Self-managed projects usually are released a week later.
    * - Service Release 1
-     - 2020-05-04
+     - 2020-05-04 (actual release 2020-05-15)
      - 2020-10-29
      - 1.5 month after Formal Release
      - Start Date +7.5 months